How Much Does Excavation Cost in Bali? 2026 Price Guide

Foreman checking excavation levels with a rotating laser on a Bali building site

“How much to dig?” is the message we get most, and the honest answer starts with three more questions: dig what, out of which ground, and where does the soil go afterwards? Those three variables move an earthworks budget by a factor of five on plots two kilometres apart. Below are our real 2026 rates, three worked budgets from sites we actually ran this year, and the places where owners quietly overpay.

The short answer: 2026 excavation rates in Bali

WorkUnitPrice (IDR)
Machine excavation, normal soilfrom 95,000
Hand digging (tight access, precision)from 300,000
Limestone / rock breaking (Bukit)380,000–550,000
Cut and fill moved on sitefrom 85,000
Soil haul-away within 10 km7 m³ truckfrom 480,000
Imported fill soil, delivered7 m³ truckfrom 660,000
Land clearing, light vegetationare (100 m²)from 550,000
Land clearing, heavy junglearefrom 2,200,000
Swimming pool pit in soil (8×4 m)packagefrom 8,500,000
Swimming pool pit in limestonepackagefrom 16,000,000
Machine trench, 60 cm deepmfrom 90,000
Septic tank, 2-chamber + soakawaypackagefrom 9,500,000

Every rate includes machine, operator, fuel and our supervision on site. The full list, including day rates and compaction, lives on the earthworks pricing page. What none of these numbers include is trucking — and that is deliberate, because trucking is where budgets are won and lost.

What you are actually buying per cubic meter

A cubic meter of excavation is not one thing. When we price a villa dig, the m³ rate covers setting out from the engineer’s drawing, the machine pass to design level, the hand trim of the last ten centimetres, and grade stakes left in the ground so your builder can verify us. Everything below is quoted separately and visibly:

  • Trucking and disposal — from 480,000 per 7 m³ load, plus 30,000/km beyond 10 km. On a normal villa this is 20–35% of the whole earthworks bill.
  • Dewatering — from 450,000/day for a pump and hoses. In Canggu, Seseh and Sanur, assume you need it; the water table is one to two metres down.
  • Mobilization — 1,500,000–2,500,000 for a flatbed to bring a machine in and take it out again. One mobilization, several jobs, is the cheapest way to buy earthworks.
  • Shoring or benching on deep cuts near a boundary — priced per job after an engineer looks at it.
  • Reinstatement — repairing the gang paving your trucks used. We include it. Not everyone does, and the banjar remembers.

Per m³ or per day: which pricing is honest

Day rates reward slow work. We price per m³ wherever the volume can be measured, which is nearly always. Machines are still quoted per day for mixed small scopes where nobody can sensibly count cubic meters:

Machine (operator + fuel included)Day rate (IDR)Realistic output
Mini excavator, PC50–75 (fits a 1.8 m gate)from 3,400,00060–110 m³
20-ton excavator, PC200 classfrom 5,400,000250–350 m³
20-ton + hydraulic breakerfrom 7,600,00015–30 m³ of limestone
Vibro roller (compaction)from 3,400,000800–1,200 m² per layer
Dump truck with driverfrom 1,900,0008–12 local trips

Do the arithmetic before you accept a day rate. A 20-ton machine at 5,400,000 that moves 300 m³ is working at 18,000/m³ of raw digging — the rest of our 95,000 is levels, hand finishing, supervision and warranty. A day rate on a crew that moves 80 m³ costs you 67,500/m³ and nobody is accountable for finishing.

The two things that really move the price: ground and access

Ground. Paddy clay in Canggu, Seseh and Sanur digs easily and holds a vertical face, but it pumps water and it sticks to everything. Volcanic loam around Ubud is the nicest material in Bali to move. Then there is the Bukit — Uluwatu, Bingin, Ungasan, Pecatu, and the upper half of Jimbaran — where a bucket bounces off coral limestone and the job becomes rock breaking at 380,000–550,000/m³. Same drawing, four to five times the price. What sits under your plot is worth reading about before you budget: see Bali soil types.

Access. The second multiplier is whether a truck can stand next to the hole. If it can, soil is loaded once. If it cannot — a gang in Canggu, a clifftop path near Bingin, a switchback driveway in the Ubud valleys — soil moves twice or three times, by mini excavator and power barrow, and the same 100 m³ costs 40–70% more. This is why we photograph access on the free site visit before writing a number.

Worked example 1: villa footings in Canggu, 96 m³

Three-bedroom villa on 3 are near Padang Linjong, strip footings to 1.1 m, truck access to the gate but not onto the plot. June 2026, rounded:

  • Setting out, levels and grade stakes — included
  • Machine excavation 96 m³ @ 95,000 = IDR 9.12 M
  • Hand trim of footing bottoms, 62 m² @ 25,000 = IDR 1.55 M
  • Dewatering, 3 days @ 450,000 = IDR 1.35 M
  • Haul-away, 10 trucks @ 480,000 = IDR 4.80 M (25 m³ kept on site for backfill)
  • Mobilization, mini excavator on a flatbed = IDR 1.50 M

Total IDR 18.3 million (~USD 1,150), three working days, footing bottoms handed over dry and inspected. A competing quote on the same drawing came in at 12 million — with no dewatering line, no hand trim and “soil to be arranged by owner”. Those three omissions are worth about seven million, and one of them is the difference between a foundation on undisturbed bearing soil and one on churned mud.

Worked example 2: a pool pit in Uluwatu limestone

Standard 8×4 m pool, 1.5 m average depth, on a plot above Melasti in Uluwatu. Eighty centimetres of red soil, then solid rock. Free test dig on day zero told us exactly that, so nothing below was a surprise:

  • Strip topsoil and weathered rock, 18 m³ @ 95,000 = IDR 1.71 M
  • Limestone breaking, 62 m³ @ 460,000 = IDR 28.52 M
  • Overdig trim, wall faces and wet-season sump = IDR 1.80 M
  • Rock spoil out, 14 trucks @ 620,000 = IDR 8.68 M
  • Mobilization, 20-ton machine plus breaker = IDR 2.50 M

Total IDR 43.2 million, eleven working days. The identical pool on a Canggu plot is IDR 8.5–12 million and three days. Same architect, same drawing, four times the earthworks — which is why every Bukit budget should be built after a test dig, not after a phone call. See pool excavation for how we sequence it around the shotcrete crew.

Worked example 3: clearing and filling 10 are in Seseh

A former rice field near Cemagi, bought cheap, needing everything before a builder could even mobilise. This is the budget owners never see coming:

  • Land clearing, 10 are @ 750,000 = IDR 7.50 M
  • Root grubbing after clearing, 10 are @ 300,000 = IDR 3.00 M
  • Cut and fill balanced on site, 180 m³ @ 85,000 = IDR 15.30 M
  • Imported fill to raise the pad 40 cm, 32 trucks @ 660,000 = IDR 21.12 M
  • Compaction in 25 cm layers, 320 m² × 2 layers @ 22,000 = IDR 14.08 M
  • Final grading of the building pad, 420 m² @ 18,000 = IDR 7.56 M
  • Temporary site access road, 60 m² @ 240,000 = IDR 14.40 M
  • Mobilization = IDR 2.00 M

Total IDR 85 million (~USD 5,200) before a single foundation was dug. Note the two biggest lines: imported fill and the road. Both are trucking. On a plot with a better internal balance we would have imported nothing — that arithmetic is explained in what cut and fill actually is.

Almost every earthworks quote that shocks an owner is a trucking quote wearing a digging costume. Count trucks first, cubic meters second.

Where owners overpay

  • Buying earthworks through a general contractor who subcontracts us anyway, at plus 25–40%. Contract the dig directly and hand your builder a finished pad.
  • Paying twice for mobilization. Excavation in March, trench for water in May, septic in July: three flatbeds, three set-ups. Combine them and the third job is nearly free.
  • Buying fill you already own. Cut from the high side of your own plot is free material. Trucking it away and buying it back costs about 1.14 million per 7 m³ round trip.
  • Approving “earthworks — lump sum”. If a quote has one line, it has no accountability. Ask for m³, truck counts and working days.
  • Skipping the test dig on the Bukit. A free half-day of digging in Uluwatu or Ungasan converts a guess into a fixed price. Owners who skip it get variation orders instead.

How to read an earthworks quote in five minutes

Take any quote — ours, or a competitor’s — and check these six things. If a line is missing, it is not cheaper; it is coming later as an extra:

  1. Volume in m³, and how it was measured (drawing, laser, drone survey).
  2. Truck count and haul distance, stated as numbers.
  3. Whether disposal is to a legal fill site — ask which one.
  4. Dewatering, if you are anywhere from Canggu to Sanur or Denpasar.
  5. Hand trim of footing bottoms, or a note saying machine-only.
  6. Working days, and what happens if rain stops the site.

For a fast sanity number before any of that: a typical three-bedroom villa on flat soil in Canggu or Pererenan runs IDR 18–28 million of foundation excavation; the same house on a sloped Pererenan gorge plot with retaining work runs 120–180 million; and on Bukit limestone, budget 2.5–4× the flat-soil figure. Then get it measured properly, because your plot is not typical.

All prices here are approximate and do not constitute a public offer. Soil, access, haul distance and season genuinely change the number. Send us a location pin and a few photos on WhatsApp — we visit free anywhere from Kedungu to Jimbaran, measure levels, calculate real volumes and send an itemised quote within 24 hours. That number is fixed in writing and does not move afterwards.

FAQ

Excavation prices in Bali — quick answers

What is a fair excavation price per m³ in Bali in 2026?

For machine excavation in normal soil with decent access: IDR 95,000–140,000/m³ including machine, operator, fuel and supervision. Below 80,000 someone is either excluding trucking or planning to leave your spoil on the plot. Hand digging is honestly 300,000/m³ and up — it is three men and a rope, not a cheaper machine.

Why does digging on the Bukit cost three to five times more?

Because it is not digging. Under Uluwatu, Ungasan, Pecatu and most of Jimbaran sits coral limestone, and a bucket does nothing to it. We mount a hydraulic breaker and chip rock out at 380,000–550,000/m³, moving 15–30 m³ a day instead of 300. We always do a free test dig first so the rock line is agreed before you sign, not discovered in week two.

Does the price per m³ include hauling the soil away?

In our quotes trucking is a separate, visible line: haul-away from IDR 480,000 per 7 m³ truck within 10 km, plus 30,000 per extra km. That is deliberate. Soil disposal is 20–35% of a typical villa dig budget, and it is the single easiest line for a cheap quote to hide. Count the trucks in any quote you compare.

Is renting an excavator myself cheaper than hiring a contractor?

Sometimes — for simple bulk work on an open site with your own competent supervision. A 20-ton machine with operator is from IDR 5,400,000/day, and a good crew moves 250–350 m³ in that day. What rental never includes is levels, setting out, hand trim, trucks, disposal permission and responsibility for the result. The full comparison is in our excavator rental guide →

How long does a villa foundation dig actually take?

With truck access to the plot: 2–3 working days for a typical three-bedroom footprint, including hand-trimmed footing bottoms. Behind a Canggu gang where soil is shuttled by mini excavator and power barrow: 4–6 days. Limestone doubles or triples that again. Our quotes state working days, not vague promises, so your builder can book the pour.